Skyview 2 Battery Storage Project Schedules Transformer Deliveries
An Ontario township update describes the planned 411 MW, four-hour Skyview 2 battery storage system and says five transformer deliveries were expected by October 6.
- Publish date: 2026-10-01
- Category: BESS & Grid Storage
- Original source: Township of Edwardsburgh Cardinal
- Reading time: 1 min
Grid Storage Project
The planned facility is designed to store 411 MW of electricity for up to four hours, shifting energy from low-demand periods to times of higher demand.
Planned Transformer Deliveries
The township said five transformer deliveries were planned between September 21 and October 6, 2026.