MV Feeder Protection Settings: 50/51, 67, 79 and IEC 60255 Evidence
A setting workflow for medium-voltage feeder IEDs covering overcurrent, earth fault, directionality, auto-reclose, CT burden, grading and minimum/maximum fault
1. Begin with Verified Inputs
IEC 60255-1:2022 states common requirements for measuring relays and protection equipment. IEC 60255-151:2009 specifies minimum requirements for overcurrent and undercurrent protection, including measurement and time-delay characteristics.
A setting file is only as good as the source data. Freeze CT ratio and class, VT ratio and earthing, feeder impedance, source minimum and maximum fault, cable thermal limit, transformer inrush, motor/inverter infeed and breaker clearing time before calculating settings.
2. Function Map
| Function | Typical purpose | Main setting risk |
|---|---|---|
| 50 / 51 | Phase instantaneous and time overcurrent | Lost selectivity or failure to detect remote faults |
| 50N / 51N | Earth-fault protection | Wrong zero-sequence path, residual CT error or excessive neutral sensitivity |
| 67 / 67N | Directional phase or earth fault | Incorrect polarizing quantity, angle convention or network operating mode |
| 79 | Automatic reclosing | Unsafe reclosing onto a permanent fault, trapped generation or an out-of-sync source |
| 50BF | Breaker-failure backup | Missing breaker status, wrong timer or inadequate upstream trip path |
3. Grading Workflow
1. Calculate the highest load, cold-load pickup, motor start, transformer inrush and permissible emergency loading.
2. Determine minimum and maximum fault current at each protected bus and the remote end of the feeder.
3. Select pickup above the declared load envelope but below the minimum fault that must be detected.
4. Apply the selected time-current curve and grade with downstream relays, fuses, reclosers and upstream protection.
5. Recheck directional elements for every source and line configuration.
Do not claim selectivity from a single fault case. The final evidence must show operating time, breaker clearing time, CT saturation margin and grading margin for all required cases.
4. Commissioning and Change Control
- Test injection, binary I/O, trip circuit supervision, breaker failure, interlocks, autoreclose block and event records.
- Confirm the relay firmware, setting group, CT polarity, phase rotation, time source and communication map.
- Store the approved setting file with the one-line revision and the source-data calculation.
- Any feeder topology, transformer tap, source contribution or CT change requires a controlled protection review.
*Reference: IEC 60255-1:2022; IEC 60255-151:2009; IEC 60255-27:2023; IEC 61850 where digital interfaces are used.*
Reproducible grading example: state the current basis
Protection coordination starts by defining the current through each relay for the same fault, not by applying the total bus fault current to every device. Parallel paths, transformer ratios, local generation and inverter infeed can change the branch contributions. Separate primary amperes, CT secondary amperes and multiples of pickup throughout the report. Review date: 12 November 2026.
For the IEC normal-inverse characteristic documented in ABB's REX610 technical manual, use t = TMS × 0.14 / ((I/Ipickup)^0.02 − 1). Here t is relay operate time in seconds; TMS is dimensionless and current is expressed on the same basis as pickup. This expression applies above pickup within the relay's declared characteristic range. It does not define a finite trip time at or below pickup, reset behaviour, a high-set stage or the breaker clearing time. Another manufacturer's similarly named curve still requires its own documentation.
Assume a radial feeder with downstream pickup 200 A primary and a 1000 A primary through-fault. A 400/1 A CT gives 2.5 A secondary fault current and 0.5 A secondary pickup: the multiple is 5 in either representation. For downstream TMS = 0.10, relay time is 0.4279720071 s. For an upstream relay deliberately assumed to see the same 5-times-pickup multiple and TMS = 0.20, relay time is 0.8559440142 s. These inputs are educational assumptions, not recommended settings.
Assume downstream breaker clearing adds 0.060 s after relay operation. Downstream total clearing is 0.4879720071 s. The available interval before the upstream relay operates is 0.3679720071 s. Comparing only the two relay times would overstate that interval by 0.060 s. An assumed grading target of 0.300 s would pass at this single nominal point; this does not establish full selectivity. The grading target, relay timing uncertainty, CT errors, breaker tolerance and safety margin must be justified for the equipment and application.
Repeat at minimum and maximum branch fault currents and around pickup transitions, instantaneous elements and any curve crossings. Include declared relay tolerances and the manufacturer's timing limits. If a fuse or MCCB is involved, use its actual minimum-melting/total-clearing or trip-band information and the applicable current-limiting/selectivity tables. A nominal IDMT equation cannot invent an OEM protection library.
CT saturation can corrupt the current waveform even when the ratio arithmetic is correct. Confirm burden, lead resistance, accuracy/limit data, remanence assumptions where relevant and the fault waveform. Directional protection needs the actual polarizing quantities, reference direction and configuration. Differential protection needs winding/CT compensation, restraint and relevant transient behaviour. Do not transfer a simple feeder timing check into those functions as evidence of their validation.
For inverter-fed networks, obtain the manufacturer fault-control envelope and relevant operating modes. A low, controlled current may not reach an overcurrent stage quickly. For motor feeders, compare starting and acceleration envelopes with the protective characteristic and motor thermal limits; a single locked-rotor current value cannot establish the complete starting trajectory. For arc-flash work, evaluate the applicable arcing-current cases and clearing paths separately.
Voltformer supports declared relay curves, branch-current screening and supported coordination studies. It does not establish OEM-approved settings or complete selectivity from this worked point. Keep the same SLD revision, source case, current basis, CT ratio, pickup, curve equation, time multiplier, tolerances and breaker opening time with the results. Project review and commissioning tests remain separate evidence.
Connect this workflow to the load-flow example, short-circuit method limits and network-validation guide. A catalog relay identifies a product family or documented configuration; it does not supply missing settings, compatible firmware or an approved protection scheme.

Programmatically calculated IEC normal-inverse curves with the declared TMS values and 0.060 s downstream breaker time; nominal curves without tolerances, not approved settings.