{
  "language": "en",
  "interfaceLanguage": "pt",
  "url": "https://voltformer.com/pt/news/enka-north-macedonia-corridors-progress-2026",
  "slug": "enka-north-macedonia-corridors-progress-2026",
  "category": "epc-contractors",
  "publishDate": "2026-09-08",
  "sourceName": "ENKA",
  "sourceUrl": "https://www.enka.com/progress-of-the-corridor-8-10d-motorway-project-as-of-august-2026/",
  "readingTimeMinutes": 2,
  "tags": [
    "ENKA Insaat ve Sanayi A.S.",
    "Bechtel Corporation"
  ],
  "content": {
    "title": "ENKA–Bechtel reports North Macedonia corridor progress",
    "summary": "Excavation and concrete volumes describe different work quantities, not a direct overall completion percentage.",
    "sections": [
      {
        "heading": "Scope of the official announcement",
        "paragraphs": [
          "ENKA–Bechtel reported 7.2 million cubic metres excavated and 130,000 cubic metres of concrete at North Macedonia’s Corridors 8/10d."
        ],
        "sources": [
          {
            "name": "ENKA",
            "url": "https://www.enka.com/progress-of-the-corridor-8-10d-motorway-project-as-of-august-2026/"
          }
        ]
      },
      {
        "heading": "Voltformer analysis",
        "paragraphs": [
          "Excavation and concrete volumes describe different work quantities, not a direct overall completion percentage. Drainage and structures need not progress on the same schedule as earthworks. Linking period quantities to work packages and inspection records makes their meaning within the project clearer."
        ]
      },
      {
        "heading": "Considerations for project teams",
        "paragraphs": [
          "Construction progress is best tracked separately for site preparation, installation, testing and operational handover. A single completion percentage cannot explain drawing approvals, material deliveries, permits or dependencies between disciplines. Work on an operating facility also needs coordination with the operator and planned shutdown windows. A useful project register links each milestone to an accountable party and its acceptance evidence. This helps teams distinguish an advancing work package from a completed facility and identify the interfaces most likely to affect the next activity."
        ]
      }
    ]
  },
  "companies": [
    {
      "slug": "enka",
      "name": "ENKA Insaat ve Sanayi A.S.",
      "href": "/pt/epc-contractors/enka",
      "website": "https://www.enka.com",
      "aliases": [
        "ENKA Insaat ve Sanayi A.S.",
        "إنكا",
        "ENKA"
      ]
    },
    {
      "slug": "bechtel",
      "name": "Bechtel Corporation",
      "href": "/pt/epc-contractors/bechtel",
      "website": "https://www.bechtel.com",
      "aliases": [
        "Bechtel Corporation",
        "بكتل",
        "Bechtel"
      ]
    }
  ]
}
