  "language": "pt",
  "interfaceLanguage": "pt",
  "url": "https://voltformer.com/pt/news/bc-hydro-energizes-500kv-step-up-transformers-site-c-substation-october-2026",
  "slug": "bc-hydro-energizes-500kv-step-up-transformers-site-c-substation-october-2026",
  "category": "renewable-integration",
  "publishDate": "2026-10-02",
  "sourceName": "BC Hydro Media Centre",
  "sourceUrl": "https://www.bchydro.com/news/press-releases/site-c-500kv-transformers-energized-october-2026",
  "readingTimeMinutes": 1,
  "tags": [
    "Canadá",
    "BC Hydro",
    "Subestação",
    "500 kV",
    "Hidrelétrica"
  ],
  "content": {
    "title": "BC Hydro energiza transformadores elevadores de 500 kV na subestação Site C",
    "summary": "A BC Hydro energizou 6 transformadores elevadores de 225 MVA a 500 kV no pátio do Projeto Site C, disponibilizando 1100 MW de hidreletricidade despachável.",
    "sections": [
      {
        "heading": "Configuração dos transformadores elevadores da usina",
        "paragraphs": [
          "A subestação de Peace River concluiu o comissionamento de 6 transformadores de 225 MVA elevando a tensão de 19 kV para 500 kV na rede básica.",
          "As unidades contam com fluidos dielétricos de éster sintético com ponto de fulgor superior a 300 °C, minimizando impactos ambientais."
        ]
      },
      {
        "heading": "Interligação com os principais centros de carga",
        "paragraphs": [
          "Dois circuitos de transmissão de 500 kV com extensão de 75 km conectam a subestação Site C à estação existente de Peace Canyon.",
          "O empreendimento fornecerá 5100 GWh por ano de eletricidade firme e limpa para atender ao consumo da província."
        ]
      }
    ],
    "tags": [
      "Canadá",
      "BC Hydro",
      "Subestação",
      "500 kV",
      "Hidrelétrica"
    ]
  },
  "companies": []
}