  "language": "en",
  "interfaceLanguage": "en",
  "url": "https://voltformer.com/news/skyview-2-bess-transformer-deliveries-ontario-2026-10-01",
  "slug": "skyview-2-bess-transformer-deliveries-ontario-2026-10-01",
  "category": "energy-storage",
  "publishDate": "2026-10-01",
  "sourceName": "Township of Edwardsburgh Cardinal",
  "sourceUrl": "https://www.twpec.ca/news/posts/skyview-2-battery-energy-storage-system/",
  "readingTimeMinutes": 1,
  "tags": [
    "Canada",
    "Ontario",
    "Skyview 2",
    "Battery storage",
    "411 MW",
    "Transformers"
  ],
  "content": {
    "title": "Skyview 2 Battery Storage Project Schedules Transformer Deliveries",
    "summary": "An Ontario township update describes the planned 411 MW, four-hour Skyview 2 battery storage system and says five transformer deliveries were expected by October 6.",
    "sections": [
      {
        "heading": "Grid Storage Project",
        "paragraphs": [
          "The planned facility is designed to store 411 MW of electricity for up to four hours, shifting energy from low-demand periods to times of higher demand."
        ]
      },
      {
        "heading": "Planned Transformer Deliveries",
        "paragraphs": [
          "The township said five transformer deliveries were planned between September 21 and October 6, 2026."
        ]
      }
    ]
  },
  "companies": []
}