EDP starts first Portuguese wind-farm repowering

EDP has begun replacing ageing turbines at Pena Suar, a €24 million project expected to raise the site’s renewable output by 143%.

EDP starts first Portuguese wind-farm repowering

EDP has begun replacing ageing turbines at Pena Suar, a €24 million project expected to raise the site’s renewable output by 143%.
  • Publish date: 2026-10-01
  • Category: Renewable Integration
  • Original source: EDP
  • Reading time: 1 min

Four new turbines

The 1 October announcement says 20 of the wind farm’s 24 turbines will be replaced by four modern units. Capacity for the repowered section rises from 10 MW to 18 MW, while the other four turbines remain in service.

EDP

Higher output, reused materials

EDP forecasts annual generation increasing from 22.9 GWh to 55.4 GWh. Work is under way, with completion planned by the first half of 2027; the company also says it has arranged specialist recycling for dismantled blades.