  "language": "en",
  "interfaceLanguage": "en",
  "url": "https://voltformer.com/news/dewa-commissions-400kv-mbr-solar-park-phase-6-substation-october-2026",
  "slug": "dewa-commissions-400kv-mbr-solar-park-phase-6-substation-october-2026",
  "category": "transmission-substations",
  "publishDate": "2026-10-04",
  "sourceName": "Dubai Electricity and Water Authority Media Centre",
  "sourceUrl": "https://www.dewa.gov.ae/en/about-us/media-publications/latest-news/2026/10/mbr-solar-park-phase-6-substation",
  "readingTimeMinutes": 1,
  "tags": [
    "UAE",
    "DEWA",
    "Substation",
    "400 kV",
    "Solar Power",
    "Dubai"
  ],
  "content": {
    "title": "DEWA Commissions 400 kV Substation to Connect Phase 6 of Mohammed bin Rashid Solar Park",
    "summary": "Dubai Electricity and Water Authority (DEWA) has commissioned a 400 kV transmission substation at the Mohammed bin Rashid Al Maktoum Solar Park to evacuate 1800 MW of solar power from Phase 6.",
    "sections": [
      {
        "heading": "Advanced Digital Substation Architecture",
        "paragraphs": [
          "The substation operates at 400 kV and 132 kV voltage levels and connects 4 autotransformers using digital process bus communications.",
          "Advanced fibre-optic relay networks provide sub-cycle differential protection and instantaneous fault isolation across all outgoing feeder bays."
        ]
      },
      {
        "heading": "Supporting Clean Energy Grid Targets",
        "paragraphs": [
          "The substation supports the Dubai Clean Energy Strategy with 100% digital protection redundancy across the central transmission corridors.",
          "High-capacity power transformers ensure efficient voltage step-up and stable dispatch into the emirate bulk supply grid."
        ]
      }
    ]
  },