Aibel’s Hornsea 3 Link 2 platform installed offshore

Aibel reported on 30 September 2026 that the second HVDC converter platform it completed for Ørsted’s Hornsea 3 wind farm had been installed offshore.

Aibel reported on 30 September 2026 that the second HVDC converter platform it completed for Ørsted’s Hornsea 3 wind farm had been installed offshore.
  • Publish date: 2026-09-30
  • Category: EPC Contractors
  • Original source: Aibel
  • Reading time: 1 min

Reported scope and milestone

Aibel: Aibel reported on 30 September 2026 that the second HVDC converter platform it completed for Ørsted’s Hornsea 3 wind farm had been installed offshore.

Aibel

Engineering interpretation

Aibel and Hitachi Energy developed the standardized 320 kV concept; engineering and project management were led from Asker, fabrication took place in Thailand, and final outfitting and commissioning were completed in Haugesund. Ørsted owns the wind farm.

Aibel

Delivery responsibilities

An EPC reference defines a contracted combination of engineering, procurement and construction. Its boundaries still matter: field facilities, pipelines and utilities may be one package within a larger development. Construction affiliates and specialist subcontractors retain their stated roles. Quality records, pressure tests, pre-commissioning and handover need to match the actual facilities delivered. A historical project schedule does not become a publication date or establish today’s production. The reference documents the listed work rather than attributing all output, ownership or operation of the wider development to the contractor.