  "language": "de",
  "interfaceLanguage": "de",
  "url": "https://voltformer.com/de/news/adnoc-taqa-lightning-project-hvdc-converter-transformers-mirfa-october-2026",
  "slug": "adnoc-taqa-lightning-project-hvdc-converter-transformers-mirfa-october-2026",
  "category": "transmission-substations",
  "publishDate": "2026-10-03",
  "sourceName": "ADNOC Media Centre / TAQA Press Office",
  "sourceUrl": "https://www.adnoc.ae/en/news-and-media/press-releases/2026/adnoc-taqa-lightning-hvdc-mirfa-transformers",
  "readingTimeMinutes": 1,
  "tags": [
    "UAE",
    "TAQA",
    "ADNOC",
    "HVDC",
    "Transformatoren",
    "Abu Dhabi"
  ],
  "content": {
    "title": "ADNOC und TAQA installieren HGÜ-Stromrichtertransformatoren für 3200 MW am Terminal Mirfa",
    "summary": "ADNOC und TAQA haben die Montage der Schwerlast-Stromrichtertransformatoren an der HGÜ-Konverterstation Mirfa im Rahmen des 3200-MW-Projekts Lightning abgeschlossen.",
    "sections": [
      {
        "heading": "Fortschritt an der Hochspannungs-Gleichstrom-Konverterstation",
        "paragraphs": [
          "Die Station nutzt VSC-Technik bei 320 kV und 2 parallele Seekabel-Übertragungssysteme mit einer Gesamtkapazität von 3200 MW.",
          "Die Spezialtransformatoren wurden für extreme Oberschwingungsbelastungen und hohe Gleichstrom-Vormagnetisierungen dimensioniert."
        ]
      },
      {
        "heading": "Dekarbonisierung von Offshore-Anlagen",
        "paragraphs": [
          "Das Projekt wird die Emissionen der Offshore-Förderung durch direkte Versorgung aus dem Festlandnetz um mehr als 30% senken.",
          "Die HGÜ-Verbindung ersetzt Offshore-Gasturbinen durch sauberen Nuklear- und Solarstrom aus Abu Dhabi."
        ]
      }
    ],
    "tags": [
      "UAE",
      "TAQA",
      "ADNOC",
      "HVDC",
      "Transformatoren",
      "Abu Dhabi"
    ]
  },
  "companies": []
}